U unreal2qaz Addict Mar 27, 2014 #1 Five jobs are waiting to be executed. their expected (running time, priority, deadline) are as follows ( 10, 5, 13), ( 15, 9, 17 ), ( 18, 12, 20 ), ( 15, 7, 23 ), ( 15, 7, 17 ) J1 J2 J3 J4 J5 Time 10 15 18 15 15 Priority 5 9 12 7 7 Deadline 13 17 20 23 17 a. Mean response time? b. Mean weighted response time? c. Minimize maximum lateness?
Five jobs are waiting to be executed. their expected (running time, priority, deadline) are as follows ( 10, 5, 13), ( 15, 9, 17 ), ( 18, 12, 20 ), ( 15, 7, 23 ), ( 15, 7, 17 ) J1 J2 J3 J4 J5 Time 10 15 18 15 15 Priority 5 9 12 7 7 Deadline 13 17 20 23 17 a. Mean response time? b. Mean weighted response time? c. Minimize maximum lateness?